On the 16 March 2026 the Technology and Construction Court (TCC) handed down judgment in the case of Laing O'Rourke Delivery Ltd (“LOR”) v Shepperton Studios Ltd (“SSL”) 16 Mar 2026 [2026] EWHC 612 (TCC), KBD.
The case arose out of an application to enforce an adjudicator’s decision and focused on a familiar issue in construction payment disputes: whether a Payment Notice and a Pay Less Notice complied with the contract’s notice requirements.
The decision is a strong reminder that (a) notice compliance is contractual, (b) a defective Payment Notice does not automatically invalidate a Pay Less Notice, and (c) parties should treat “basis of calculation” as a requirement to provide meaningful build-up detail, not just a bottom-line number. This case is a reminder to the industry of the importance of getting payment notices correct.
LOR submitted an interim payment application for circa £5.62 million. In response, SSL issued a payment notice which stated a gross valuation and a net sum due but did not explain how the gross valuation was built up, nor did it expressly incorporate a supporting valuation breakdown by reference.
SSL then served a pay less notice, setting out deductions for liquidated damages, utilities, and catering, reducing the balance to £0, and included detailed information explaining the basis of those deductions.
The Adjudicator found that both the payment notice and the pay less notice were invalid and ordered SSL to pay the full circa £5.62 million. The dispute then came to court in enforcement proceedings, alongside Part 8 declaratory proceedings challenging the adjudicator’s approach.
The Court ultimately ruled that SSL’s payment notice was invalid due to its failure to detail the basis of calculation of the gross valuation, which was required by the contract. The contract required a Payment Notice to state (i) the sum the payer considered due at the due date, and (ii) the basis on which that sum has been calculated. The TCC held that this requirement meant more than stating a gross valuation figure and arriving at a net amount due.
The Court decided that the Pay Less Notice was valid, meaning that SSL was entitled to make the stated deductions. The Court held that the Pay Less Notice contained sufficient detail, and that it did not matter that the Payment Notice was invalid. Because the Payment Notice was invalid, but the Pay Less Notice was valid, the Court enforced the adjudicator’s decision only to the extent of the balance due after deducting the items in the Pay Less Notice.
This judgment is a stark reminder of the importance of getting payment notices correct and following the contract.
Holmes & Hills LLP supports developers, contractors, and consultants with payment disputes and defective notices. Speak to our Construction Law Team for specialist guidance.
Call us on 01206 593933 today to speak with one of our construction law team. Or complete the form below.
Disclaimer
The content of this article is provided for general information only. It does not constitute legal or other professional advice. The information given in this article is correct at the date of publication.







A Mackman Group collaboration - market research by Mackman Research | website design by Mackman