Sophie Bennett, Associate at Holmes & Hills, discusses the lessons learned from the COVID-19 pandemic and how the JCT 2024 suite of contracts has responded to the construction industry's experience of unprecedented disruption.
The COVID-19 pandemic was arguably the most significant disruption to the global construction industry in living memory. From nationwide lockdowns and supply chain collapse to labour shortages and increasing material costs, few projects escaped unscathed. In the years since, the industry has reflected on the contractual mechanisms that were (and were not!) adequate to deal with such an event. The JCT 2024 suite of contracts represents the first major revision of the JCT standard forms since the pandemic, and its introduction of an express epidemic and pandemic Relevant Event is one of the most noteworthy developments.
When the UK Government announced the first national lockdown in March 2020, the construction industry was plunged into uncertainty. While construction was never formally ordered to cease, many sites closed voluntarily or became unworkable due to social distancing requirements, the unavailability of key workers, and the closure of material suppliers.
The consequences were far-reaching:
Under the JCT Design and Build Contract 2016, parties seeking to claim extensions of time for pandemic-related delay were forced to rely on Relevant Events that had not been drafted with a public health emergency in mind. The most commonly invoked grounds included:
The absence of an express pandemic or epidemic clause left both employers and contractors in an unsatisfactory position, reliant on contractual interpretation and, in many cases, negotiated ad-hoc solutions.
Recognising these shortcomings, the JCT 2024 suite introduces an express Relevant Event for epidemics and pandemics. This new clause entitles the Contractor to an extension of time where the progress of the Works is delayed by the effects of an epidemic limiting the availability or use of labour or the securing of goods or materials necessary for the carrying out of the works.
This is a significant and welcome development for several reasons:
It should be noted, however, that the new Relevant Event provides for time relief only. Consistent with the existing structure of the JCT delay provisions, an epidemic or pandemic is not listed as a Relevant Matter entitling the Contractor to loss and expense. The financial risk of such events therefore remains with the Contractor.
Despite the improved drafting, parties should not regard the new clause as a complete solution. Key points include:
COVID-19 exposed significant gaps in the standard form construction contracts that had served the industry for decades. The JCT 2024 introduction of an express epidemic and pandemic Relevant Event is a direct and practical response to that experience. While it does not resolve every issue, it provides a stronger foundation for managing delay in the event of a future public health emergency.
Call us on 01206 593933 today to speak with one of our construction law solicitors. Or complete the form below.
Disclaimer
The content of this article is provided for general information only. It does not constitute legal or other professional advice. The information given in this article is correct at the date of publication.







A Mackman Group collaboration - market research by Mackman Research | website design by Mackman